The owners of a discount motel chain are considering building a new motel. Optimistic, pessimistic, and most likely estimates of several key parameters have been obtained from the local builders and the chamber of commerce. These estimates are shown in the table below. The life of the motel is estimated to be 15 years, and MARR is 20%.

ParameterPessimisticMost LikelyOptimistic
Initial Cost$9,800,000$9,275,000$5,500,000
Annual Operating$360,000$170,000$180,000
Annual Revenue$1,700,000$1,500,000$2,800,000

Based only on the pessimistic estimates, is the new motel economically attractive?

Please enter the PW used to reach your decision: 

Based only on the most likely estimates, is the new motel economically attractive?

Please enter the PW used to reach your decision: 

Based only on the optimistic estimates, is the new motel economically attractive?

Please enter the PW used to reach your decision: 

Based on a beta approximation of expected value estimates, is the new motel economically attractive?

Please enter the PW used to reach your decision: